Out of 19.5 kilometres of underground electricity cabling taken up in Katak city during the current 2026–27 financial year under TP Central Odisha Distribution Limited’s (TPCODL) capital expenditure (CAPEX) programme, 14.5 kilometres of work has already been completed at a cost of ₹2.80 crore, Deputy Chief Minister and Energy Minister Kanak Vardhan Singh Deo informed the Odisha Legislative Assembly.
In a written reply to an unstarred question (Question No. 09) raised by Barabati-Katak MLA Sofia Firdous, the Deputy Chief Minister shared a detailed status report on ongoing underground power infrastructure upgrades across the city, including dedicated high-voltage transmission lines linked to the SCB Medical College and Hospital (SCBMCH) redevelopment project.
SCBMCH Redevelopment Lines & 33 kV Feeder Timelines
Highlighting parallel high-capacity transmission works executed by the Odisha Power Transmission Corporation Limited (OPTCL), Singh Deo placed key project milestones before the House:
- 132 kV Cabling Completed: As part of the SCBMCH redevelopment initiative in Katak, OPTCL completed the 132 kV underground cable laying work in March 2026.
- 33 kV Feeder Targets: Out of five 33 kV underground cable feeders planned for the project, construction of two feeders has been completed, while the remaining three feeders are targeted for completion by January 2027.
Phased Shift From Overhead Wires to Underground Cables
Addressing broader queries on replacing overhead power lines with underground networks in Katak, the Deputy Chief Minister clarified that the state government and distribution utilities are undertaking a phased, need-based transition from overhead wires to underground cabling to strengthen power supply reliability and urban safety.